Project Name: Rio Vista Falls Maintenance

Current Update: 11/2021

Work Completed Last Month: Crews mobilized in October, and installed erosion controls and construction site fencing. A temporary cofferdam was installed so the gates on the bypass pipes could be tested.

Work Planned This Month: In November crews will be setting up the bypass pipe outfall along trhe riverbed protection near the Cheatham Street bridge. The dewatering process will begin towards the end of the month and restoration work will begin on the uppermost spillway/pool.

Construction Completion: See Dashboard for Details

Pictures from last month:

Cofferdam setup for testing gatesSweeping for Fountain DartersCofferdam setup for testing gates (2)