Project Update

Project Name: Guadalupe Street Improvements - Sidewalk and Landscaping

Current Update: 09/2021

Work Completed Last Month: Silva cells and San Marcos Electric Utility (SMEU) duct bank installation

Work Planned This Month: Installation of SMUE transformer pads, pedestal pads, cables, and pedestrian lighting foundations  

Construction Completion: See Dashboard for Details

Pictures from last month