Uhland Road Improvements

Current Update: 06/2021

Work Completed Last Month: Phase 1 (of 4) work includes – Fiber optic relocation complete by telecom firms. More junction boxes completed for storm water and work continued on headwall. Approximately 80% of waterline work complete in Phase 1. More existing sidewalk in and curb removed. 

Work Planned This Month: Continue stormwater construction in Phase 1. Start on road construction. Start on gas relocation. Complete waterline work in Phase 1.  

Construction Completion: See Dashboard For Details

Pictures from last month
Pavement removal in Uhland-River Intersection3Storm pipe stored on River rdView SE on Uhland towards low water crossing