Schedule and Budget

  • Phase 1 (Preliminary Engineering Report) started May 2018
  • Neighborhood Public Meeting – July 18, 2018
  • Phase 1 (Preliminary Engineering Report) completed – January 2019
  • Phase 2 - Design starts May 2019
  • Phase 2 - Design anticipated to be completed February 2020
  • Construction anticipated to start late 2020
  • Construction Cost (estimate) $3,000,00