Project Update - October 2019 

  • Asphalt is scheduled for Friday 10/25 for San Antonio & Travis Streets (Rain could push it to next week)
  • All underground is complete (Storm and utilities)
  • Travis Street concrete work is complete
  • San Antonio Street will begin concrete curb, sidewalks and driveways after 1st course of asphalt – 2 weeks
  • Final courses of asphalt will then be installed ~ 4 weeks to completion
  • Pond work is underway in Dunbar park...grading, rock rip rap, etc. ~ 4 weeks to completion


***Halloween Update***

Access through the work area will be open to Trick or Treaters on foot, 

cars will not have thru access on San Antonio Street