**All dates are based off an estimated monthly schedule and are weather dependent**

Wastewater

  • No wastewater work is scheduled for this month

Water

  • Water main installation along Patton, Railroad tracks to Roosevelt and Armstrong to Wavell.  Water services installation along Wavell and Water line tie-in at Alabama at Ellis St and Arizona.

Street Work

  • Roadway excavation, flex base installation and preparations for concrete work continue on Alabama, Arizona, Georgia, Gomez and Railroad Streets