Project Update - May 2019 

  • Construction on CM Allen is behind the original schedule, due to weather delays and unanticipated conflicts with existing utilities
  • The final water and wastewater improvements are underway, and completion is anticipated by the end of the month, weather permitting
  • Crews expect to pour the first layer of asphalt on the roadway at the end of May or early June