Project Update - 

  • Public Meeting - Environmental Document - February 6, 2020 - 6:00 pm at Activity Center, 501 E Hopkins
  • Completed Draft Preliminary Engineering Report
  • Completed Draft Engineering Feasibility Report and submitted to Texas Water Development Board
  • Applied for additional funding for project through TWDB
  • Completed DRAFT Environmental Information Document and submitted to Texas Water Development Board
  • Environmental Assessment in progress for submittal to HUD

On September 12, 2018, the second Blanco Riverine Flood Mitigation community meeting was held at the San Marcos Activity Center. Below are links to the presentation given at the meeting, in English and Spanish:

September 12 Community Meeting Presentation - English (PDF)

September 12 Community Meeting Presentation - Spanish (PDF)

Proposed Blanco Riverine Mitigation 121518