Schedule and Budget

  • Schematic Design & Environmental Clearance:   April 2017-Fall 2019
  • Final Design & Land Acquisition:   Fall 2019-Spring 2021
  • Construction: tbd

Budget:   $11.5M

Current Funding:

  • TWDB = $1,961,821
  • CDBG-DR (2017) = $6,971,200
  • City (2019) = $2,628,800

Project Manager: Laurie Moyer