Schedule and Budget

  • Final Design and Environmental Clearance: Spring 2019  
  • Utility Relocations (Telecommunications and gas): Pending land acquisitions
  • Construction: Follows utility relocations. Currently late 2020
  • Construction End: Spring 2021
  • Construction Cost: $6,500,000
  • Project Manager: Kirk Abbott
  • For more information on this, or any other City Project, email us at enginfo@sanmarcostx.gov