Project Update 

  • 100 Percent Design plans are complete
  • Environmental Assessment in accordance with HUD requirements will be complete in September 2019  
  • Construction anticipated Spring/Summery 2020 pending ROW acquisition
  • Sand and Gravel Permit submitted in August 2019 from Texas Parks and Wildlife Department
  • Sec 10-404 Permit application has been submitted to USACE
  • Final Floodplain notification issued September 8th


Previous milestones

  • Preliminary Engineering Report (PER) completed March 2018
  • Neighborhood meeting at Calvary Baptist Church June 11, 2018