Old RR12 Bike / Pedestrian & Widening

Background & Schedule


  • 2010 - CAMPO awarded Funds to the City
  • Federal government reimburses the City $99,000 with a local match of match of $101,000
  • Build bike and pedestrian improvements along Old Ranch Road 12 from Hughson to Holland
  • 2013 - Scope was expanded and preliminary engineering report completed
  • Extended limits; revised limits where changed to Craddock to Holland
  • Road widening added
  • Water and wastewater scope added
  • Water Quality/Lid features added
  • 2014 - Project delayed
  • 2015 - Bike lane survey concluded and drainage investigation complete

Delay


Project was delayed until surrounding construction is completed
Drainage Scope was expanded to address off-site issues
$99,000 in CAMPO funds were transferred to Sessom Sidewalk Project

Public Meeting scheduled for February 24, 2016.

Schedule


  • 2018 - Start Construction
  • 2020 - End Construction