Project Name Construction Cost (Estimate until Under Contract) City Project Manager Design Firm Anticipated Construction Start Date
Bishop Sidewalk
(Prospect to Belvin)
 $400,000

Shaun Condor

 LJA

Summer 2018 

Blanco Gardens Drainage Improvements $5,500,000 Rey Garcia Scheibe Consulting Fall 2018
Cheatham Street and Blanco River Waterline Bore Improvements $1,200,000 Kirk Abbott  K. Friese & Associates Winter 2018 
City Park Bio Filtration Pond $350,000 Rey Garcia John Gleason, LLC Winter 2017
CM Allen Parkway Reconstruction $267,000
Greg Schwarz
 Vickrey & Associates
 Fall 2017
Coers Drive Improvements 
$1,700,000
Shaun Condor
Lockwood, Andrews & Newnam, Incorporated
Summer 2018
Cottonwood Creek 24 inch Waterline
$2,500,000
Richard Reynosa
 C P & Y
Winter 2017 
Hopkins Street Improvements - Bishop to Moore
$13,700,000
Richard Reynosa
 Freese & Nichols
Fall 2018
Hutchison Water Quality Pond Repair $85,000 Rey Garcia John Gleason, LLC Spring 2018
McKie and Lee Street Waterline Replacement
$600,000
Shaun Condor
Weston Solutions, Inc.
Fall 2017
Mill Street Improvements $3,300,000 Rohit Vij Unitech Winter 2018
Old RR 12 Bike and Pedestrian Widening
$4,200,000
Shaun Condor
Halff Associates, Incorporated
2019
Reclaimed Water Expansion - Elevated Storage Tank $1,800,000 Rey Garcia RPS Winter 2018
Reclaimed Water Expansion - Pump Station Upgrades $600,000 Rey Garcia RPS Winter 2018
River Road Pavement and Bank Stabilization Project  
$300,000  
Rey Garcia
Alan Plummer Associates
Fall 2017
Sessom Creek Wastewater Replacement - N LBJ to Comanche
$1,500,000
Shaun Condor
Kimley Horn & Associates
Winter 2020
Sewer System Evaluation Studies (SSES) $2,400,000 Kirk Abbott Burgess & Niple Winter 2018
Victory Gardens Subdivision
$10,386,932
Rey Garcia
Bain Medina Bain Engineers
Fall 2017
Wallace Addition Water and Wastewater Improvements 
 $1,550,000
Rohit Vij
Klotz Associates
 Winter 2017