Projects In Construction

Pedestrian improvement on CM AllenC M Allen Parkway Reconstruction

  • CM Allen roadway was reopened to traffic in December 2019
  • Landscape maintenance is ongoing, and crews will be on-site periodically to tend to the plants
  • As-built drawings are currently under review, and final walk-through will be conducted in the near future

Doghouse manhole after concrete pourHills of Hays Lift Station Rehabilitation

  • Contractor has mobilized to the site. 
  • Construction started on manhole to bypass lift station and bypass valve over existing force main. 
  • Bypass pumping will start beginning of December 2020 to enable work to start on lift station rehabilitation. 
  • Contract expended = 0%

Construction completion Spring 2021


Hopkins Before Photo ADA Ramp Opens in new windowE Hopkins - Bike and Pedestrian Improvements

  • Contractor is expected to start installing erosion control devices and surveying the job in mid-November
  • Contractor will start sidewalk between Charles Austin and Thorpe after erosion controls are installed


Construction completion Summer 2021

hydrant at Travis Opens in new windowHopkins Street Improvements - Bishop to Moore

  • Construction continues on Phase 1 (Johnson Ave. to Scott St). Phase 2 (Bishop to Johnson Ave.) is expected to begin in December.
      • Phase 1 storm sewer is 100% complete.
      • Phase 1 wastewater is 90% complete.
      • Phase 1 water installation is 90% complete.
      • Phase 1 asphalt is 0% complete.
      • Phase 1 concrete is 0% complete.
      • Phase 1 lighting is 0% complete.

% Contract Expended: 18.4%

Construction Completion Spring 2022

Fusible PVC pipe for force mainMain Lift Station Force Main Replacement

  • Construction alongside River Road
  • Diversion channel is complete
  • Two 24” force mains 30% complete (slight delays due to pipe realignment caused by unforeseen conflicts/conditions of existing utilities)
  • 5’x5’ storm culvert along River Rd 80% complete
  • Remaining 5’x5’ culvert and six storm sewer crossings to be installed following the completion of both force mains

                                                                            % Contract expended = 29%

Construction completion Spring 2021

Reclaimed Water Pumps Reclaimed Water System Expansion

Elevated Storage Tank and 3 Reclaimed Water Pumps Complete

SCADA (supervisory control and data acquisition) programming underway

Final punch list items in process

Elevated Storage Tank, % Contract expended = 98%

Pump Station Upgrades, % Contract expended = 98%



Construction completion November 2020

Victory Gardens Subdivision Improvements1 Opens in new window

Working on Alabama, Arizona, Armstrong, Eisenhower, Gomez, Railroad, Rodriguez, Roosevelt & Wavell 

Wastewater 95% complete 

Water 95% complete

Stormwater 60% complete

Rain gardens 70% complete

Road work 70% complete

% Contract expended = 73%

Construction completion February 2021

 


Wonder World/Hunter Preferred Alternative

Wonder World at Hunter Road Intersection Improvements


  • Total project cost is $529,832.56
  • Contractor will be placing detour signs and erosion control at the intersection in mid to late November
  • Intersection Improvements project includes the construction of a pedestrian refuge island, sidewalks and curb ramps, installation of pedestrian signal poles and new striping for bicycle lanes

Individual corners of the intersection will be constructed one at a                   time so that there is minimal disruption to the traffic

Construction completion January 2021