Project Update

Project Name: Main Lift Station Force Main Replacement

Current Update: 09/2021

Work Completed Last Month: Storm sewer crossings along River Road

Work Planned This Month: Complete storm sewer crossings along River Road, remove traffic controls and begin punch list items

Construction Completion: See Dashboard For Details

Pictures from last month