About the Project

Kingwood Street and Sherwood Drive are located in southwest San Marcos and connect to the TxDOT IH 35 frontage road. They are within the Willow Springs Creek watershed.  The project will reconstruct both streets, upgrade the existing water and wastewater systems, and construct a new street drainage system. The project will also evaluate sidewalks and stormwater quality treatment facilities.

The project will be conducted in the following phases:

Design Phase

Phase 1 – Conduct preliminary engineering to determine street, drainage, water and wastewater requirements.  This phase will include conducting a public meeting, field investigations including topographic surveys and estimated construction costs.

Phase 2 – Develop designs, construction documents and specifications considering  findings.

Construction Phase

Construct proposed improvements