Project Update - May 2020

  • Contractor pre-construction meeting scheduled for May 2020
  • Anticipated Construction Start – Summer 2020
  • Hopkins through traffic to be detoured at Moore Street to Craddock and at Bishop street to Craddock
  • 1st Phase of Construction limits Endicott to Johnson
  • Proposed improvements can be found here

The Hopkins Street Improvements from Bishop to Moore Streets will replace existing water and wastewater infrastructure, add a drainage system to improve storm water runoff, and reconstruct the street with curbs and sidewalks.

Improvement rendering of street scene

Design Process

The City of San Marcos is in the design process to reconstruct Hopkins Street between Moore and Bishop Streets, and to identify ways to improve drainage in the neighborhood.

Approach

A "Complete Street" approach will be used in the design of Hopkins Street, with considerations to:

  • Existing heritage trees
  • Pedestrian and bicycle traffic
  • Streetscape and gateway elements to enhance the historic neighborhood
  • Traffic calming
  • Utility considerations

Drainage

Drainage in the neighborhood will be analyzed to determine needed upgrades in the system.