Schedule & Budget

  • Construction Start: Summer 2017
  • Pipeline: Construction complete May 2019
  • Elevated Storage Tank: Construction complete by October 2019
  • Pump Station Upgrades: Construction start September 2019 complete by January 2020

Construction Cost:

  • Pipeline: $5,278,000
  • Elevated Storage Tank: $1,870,000
  • Pump Station Upgrades: $892,000


Rey Garcia, P.E. is the project manager. Email Rey Garcia.