Victory Gardens Subdivision - October 2020

**All dates are based off an estimated monthly schedule and are weather dependent**

  • Wastewater: Wastewater main installation along Patton from Roosevelt to Railroad
  • Water: Water main installation along Patton from Roosevelt to Railroad, from Stillwell to Invasion and along Knox
  • Storm: Storm sewer installation along Patton from Roosevelt to Hines
  • Street Work: Roadway excavation, flex base installation and preparation for concrete work in progress on Alabama, Arizona, Armstrong, Georgia, Gomez, Railroad, Rodriguez and Wavell Streets.  Asphalt installation along the West side of Patton anticipated to begin October 19
  • Rain Gardens: Installation of bio-filtration media, plantings and underdrain system this month

If you would like to receive project updates by email please send your email address to: enginfo@sanmarcostx.gov 

October Monthly Construction Update_Page_1
October Monthly Construction Update_Page_2

We're here if you need us: 

After hours - David VanDyke, Cox Construction - 512.618.2249

Damage claims - Cindy Conyers, City of San Marcos - 512.393.8065

Towing issues/expenses - Rey Garcia, City of San Marcos - 512.393.8143

General questions, concerns - Nancy Hyde, City of San Marcos - 512.393.8130